GENERAL INFORMATION
Site Area Acres:
1.71
Is Site on an NCDOT (State) Maintained Road?:
No
Is this a revision to an approved set of plans (RTAP)?:
No
Jurisdiction:
Charlotte
Development Type:
Non-Subdivision
Additional Parcels:
15302513, 15302514, 15302510, 15302519
Disturbed Acreage :
1.71
Is this a Housing Trust Fund Project?:
No
Water/Sewer provider:
Charlotte Water
Is there an associated conditional rezoning?:
No
UDO Primary Zoning:
NC Neighborhood Center Zoning District
Overlays:
N/A
ZONING INFORMATION
Does this project require a UDO bonus?:
Yes
UDO Bonus Presubmittal Meeting Record ID:
LDPSM-2023-00095
Electric Vehicle Charging Stations:
Yes
CATS INFORMATION
Is this project along an existing bus route?:
Yes
Is this project along an existing light rail line?:
No
URBAN FORESTRY
Do you have existing ROW trees?:
Yes
Is this site requiring tree protection fencing?:
Yes
Do you have any Heritage trees?:
No
Do you have previously approved Tree save?:
No
STORM WATER
Does the site have an SCM/BMP?:
No
Does the FEMA/Community Floodplain exist on the parcel(s)?:
No
Does this site have any walls for the SCM or Culverts?:
No
Does this site propose any grading off of the subject site?:
No
Does this project impact any stream/wetlands?:
No
Does this project impact a Water Quality/SWIM Buffer?:
No
Does this project require a Storm water 100+1 study?:
No
Does this project impact an existing Storm Water SDE?:
No
CDOT INFORMATION
What is the centerline length of new sidewalk along arterials?:
0
Are project limits within 350 FT radius of an existing traffic signal?:
Yes
Does project modify an existing traffic signal?:
Yes
Does project modify or add a bridge?:
No
Does project modify or add a culvert wider than 20 linear feet?:
No
What is the trip generation for the project?:
2440
Is a traffic impact study required for this site?:
Yes
Is a Transportation Demand Management Assessment required for this site:
No
Is there a number of Multi-Modal mitigation points required for this site? :
No
Are there off-site transportation improvements (including any form of monetary commitments) required?:
No
Is this site adding new curb ramps or replacing existing curb ramps?:
Yes
Number of curbs ramps to be added/replaced:
1
PLAN ROOM ACKNOWLEDGEMENT
I acknowledge that I will upload plans, supporting documentation, and attachments following the submission of my application.:
Yes