ADVISORY COMMENTS |
Type: condition Title: Note for new development on site Description: Provide a note stating that any new development on site outside of the existing building and parking on site will comply with the current zoning ordinance. Discipline: LD Zoning Status: Open Target: RZ-1 CreatedByName: Jennifer Frixen CreatedDate: 11/28/2022 6:56PM LastUpdateBy: Jennifer Frixen LastUpdatedDate: 11/28/2022 6:58PM |
Type: condition Title: Maximum number of units allowed? Need to include this information to show that density works for the proposed district. Discipline: LD Zoning Status: Open Target: RZ-1 CreatedByName: Jennifer Frixen CreatedDate: 11/28/2022 6:42PM LastUpdateBy: Jennifer Frixen LastUpdatedDate: 11/28/2022 6:43PM |
Type: condition Title: Show setbacks and yards as labeled in text comments on site plan. Discipline: LD Zoning Status: Open Target: RZ-1 CreatedByName: Jennifer Frixen CreatedDate: 11/28/2022 7:03PM LastUpdateBy: Jennifer Frixen LastUpdatedDate: 11/28/2022 7:06PM |
Type: condition Title: Open Space Description: Site will need to provide a min of 30% open space. Discipline: LD Zoning Status: Open Target: RZ-1 CreatedByName: Jennifer Frixen CreatedDate: 11/28/2022 7:07PM LastUpdateBy: Jennifer Frixen LastUpdatedDate: 11/28/2022 7:31PM |
Type: condition Title: Parking Screening Description: Parking will need to be screened from public R/W and abutting properties. Discipline: LD Zoning Status: Open Target: RZ-1 CreatedByName: Jennifer Frixen CreatedDate: 11/28/2022 7:27PM LastUpdateBy: Jennifer Frixen LastUpdatedDate: 11/28/2022 7:31PM |
Type: condition Title: Section 9.303(19)(c) Description: If any parking is moved on site internally, all buildings will need to comply with Section 9.303(19)(c). Please add this note to the plans. Discipline: LD Zoning Status: Open Target: RZ-1 CreatedByName: Jennifer Frixen CreatedDate: 11/28/2022 7:29PM LastUpdateBy: Jennifer Frixen LastUpdatedDate: 11/28/2022 7:31PM |
Type: condition Title: Dimension R/W Description: Setback is measured from the full R/W (minimum required is 50' from CL). Show how much R/W exists. If less than 50' from CL exists, need to show R/W dedication and 30' setback from there. If more than 50' from CL exists, show 30' setback from current R/W line. Discipline: LD Zoning Status: Open Target: RZ-1 CreatedByName: Jennifer Frixen CreatedDate: 11/28/2022 7:30PM LastUpdateBy: Jennifer Frixen LastUpdatedDate: 11/28/2022 7:31PM |
Type: condition Title: Location of existing parking along Sunset and Millhaven Description: Please add notes to the site plan stating that no expansion or grading of parking can take place within the setback along these R/Ws Discipline: LD Zoning Status: Open Target: RZ-1 CreatedByName: Jennifer Frixen CreatedDate: 11/28/2022 6:45PM LastUpdateBy: Jennifer Frixen LastUpdatedDate: 11/28/2022 6:45PM |
Type: condition Title: Garbage/Recycling requirement Description: Eleven (11) or less residential units - eligible under Chapter 10 of the City Code, as amended, for small container solid waste services.
Twelve (12) or more residential units, eligible under Chapter 10 of the City Code, as amended, for large container (e.g. dumpster(s)/compactor) solid waste services; however, the property must provide a large container (e.g. dumpster(s)/compactor). Any recycling carts shall be placed near any large container (e.g. dumpster(s)/compactor). The minimum space allocation shall be an eight (8) cubic yard dumpster-type of large waste container per every thirty (30) units or an eight (8) cubic yard compactor-type of large waste container per every ninety (90) units.
Required space allocation for recycling stations in multi-family developments
Number of Units
Allocate space for:
Approximate Sq. footage required
0âโฌโ11
No space required
No space required
12âโฌโ80
One recycling station
144 sq. ft.
81âโฌโ160
Two recycling stations
2 Ãโ 144 sq. ft. (288 sq. ft. total)
161âโฌโ240
Three recycling stations
3 Ãโ 144 sq. ft. (432 sq. ft. total)
241âโฌโ320
Four recycling stations
4 Ãโ 144 sq. ft. (576 sq. ft. total)
321âโฌโ400
Five recycling stations
5 Ãโ 144 sq. ft. (720 sq. ft. total)
401âโฌโ480
Six recycling stations
6 Ãโ 144 sq. ft. (864 sq. ft. total)
For each subsequent group of 80 units, space for one recycling station must be added.
Each recycling station represents space for five 96-gallon carts and is approximately 144 sq. ft. Space for recycling stations may be distributed throughout the development, however, space for each individual station must equal 144 sq. ft. with a minimum width of 34 inches and accommodate five 96-gallon carts.
Space requirements for dumpster(s)/compactor and recycling is required to be set aside even if property owner and/or developer elects to use a private hauler for individual rollout cart service. Discipline: Solid Waste Status: Open CreatedByName: Mavis Gant CreatedDate: 11/8/2022 3:14PM LastUpdateBy: Mavis Gant LastUpdatedDate: 11/8/2022 3:14PM |
Type: condition Title: Proposed District Description: Should read R-43MF Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 8:39AM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Zoning District Title Description: The Ordinance uses the title R-43MF to describe the district. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 8:38AM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Typo Description: "The" Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 8:39AM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: note Title: Notes Description: Charlotte Water has accessible water system infrastructure for the rezoning boundary via an existing 12-inch water distribution main located in Milhaven Lane.
Charlotte Water has sanitary sewer system infrastructure accessible for the rezoning boundary via existing 8-inch gravity sewer main within Milhaven Lane
Development is encouraged to contact Installation Development Services at (704) 336-5499 to review service connection design requirements and City Ordinances (e.g., backflow, separate meter Ordinance, public/private pipeline extensions). Comments: Has direct access to sewer. Has direct access to water. Contact CLT Water New Services Department for water/sewer services. Contact CLT Water Donated Projects if public infrastructure will be extended through property.
Reservation of sanitary sewer system capacity through the Charlotte Waterâโฌโขs Capacity Assurance Program is the responsibility of the customer/development. Contact the New Services Group at
(704) 432-2854 for further information on reserving capacity up to 24 months.
Discipline: Charlotte Water Status: Open CreatedByName: Alan Gaines CreatedDate: 11/28/2022 12:36PM LastUpdateBy: Alan Gaines LastUpdatedDate: 11/28/2022 12:36PM |
Type: condition Title: Open Space Description: Please describe any proposed open space dedication beyond what is required by the Zoning Ordinance. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 1:11PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Fire Requirements Description: Future site plan submittals shall comply with the following as it applies to the project:
R-2 - Sprinklered Apartments âโฌโ ISO Calculations
An ISO needed fire flow (NFF) calculation shall be completed for all sprinkled buildings, NFPA 13D and NFPA 13R Systems.
Buildings protected with an NFPA 13R sprinkler system shall be calculated with a 50% credit allowance given on the NFF.
Fire Department Connection Access âโฌโ
The fire department connection (FDC) shall not be greater than 50 feet from a fire department access road.
NFPA 13 / NFPA 13R FDC âโฌโ
Show an NFPA 13 / NFPA 13R FDC location within 200 feet of a fire hydrant as the truck travels.
Hydrant Locations âโฌโ
Show all existing and new hydrant locations, including size of mains. Friction loss calculations shall be required for all new hydrant installations in a water-model format; label hydrants whether they are public or private.
Hydrant Flow Test âโฌโ
Include recent hydrant flow test (within the past 12 months) of the closest hydrant serving the proposed building. Flow calculation shall be at 20 psi from our hydrant test coordinator by calling 704-336-2101.
Water Model âโฌโ
A water model will be required for the proposed hydrants. Friction loss calculations shall be required for all new hydrant installations in a water-model format; label hydrants whether they are public or private.
Discipline: Fire Status: Open Target: RZ-1 CreatedByName: Kevin Esposito CreatedDate: 10/31/2022 8:58AM LastUpdateBy: Kevin Esposito LastUpdatedDate: 10/31/2022 8:58AM |
Type: condition Title: Tree Ordinance Description: Add note stating that "Site shall comply with the requirements of the City of Charlotte Tree Ordinance" Discipline: Urban Forestry Arborist Status: Open Target: RZ-1 CreatedByName: Henry Kunzig CreatedDate: 11/28/2022 5:29PM LastUpdateBy: Henry Kunzig LastUpdatedDate: 11/28/2022 5:29PM |
Type: condition Title: Show Layout/Describe Use of South Parcel Description: Please show layout of proposed parking, buffers, tree save areas, and future development areas. Specify proposed future uses. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 2:13PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Parking Description: The note of parking as required by ordinance is good. But please include existing number of parking spaces and show on the site plan where any additional spaces will be provided. The Hotel ratio is one per room and the multi-family ratio is 1.5 per dwelling unit. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 1:15PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Future Right-of-Way Description: Please provided condition to dedicate right-of-way to meet or exceed required transition setback. The Required transitional setback along Millhaven Lane is 35 feet. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 1:17PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Internal Pedestrian Improvements Description: Are any pedestrian improvements proposed internal to the site? Consider addition of sidewalk of pedestrian circulation between existing structures and along primary internal drive. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 1:20PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Existing Building Description: What is proposed for the existing building? Renovation for another restaurant? Please specify future use of this parcel and plans for existing building. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 2:18PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Future Use of Existing Parking Area Description: Please describe future use of existing parking area. Will it remain parking or is it proposed as a future development area? Or some other use? Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 2:27PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Add to Site Data Table Description: Current number of hotel rooms, proposed number of dwelling units, proposed maximum number of dwelling units. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 2:48PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Proposed Uses Description: Will multi-family be the only use on the site? There is an existing vacant restaurant building on the site and two vacant parcels that could potentially see future development. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 3:05PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Reserved Sections Description: Please add conditions to these sections or remove from plan. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 4:47PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Hotel Use to Cease Description: Please add condition that states the hotel use will cease prior to first multi-family unit being made for available for lease. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 4:52PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Architectural Standards Description: Elaborate on standards such as maximum height, building material etc. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 5:07PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Streetscape Description: Please specify any conditions related to proposed streetscape improvements. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 5:08PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Class I Street Buffer Description: A street buffer is required adjacent to Class I streets such as I-77 in accordance with Section 12.307 of the Zoning Ordinance. Please depict on site plan or add as condition. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/23/2022 5:09PM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Setbacks/Yards Description: Note and show required setbacks and yards. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/30/2022 11:50AM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: is this development or redevelopment as you used in the purpose statement? Description: any new buildings, if proposed, should not be constructed in a similar fashion as the ones that exist. Discipline: Urban Design Status: Open Target: RZ-1 CreatedByName: Will Linville CreatedDate: 11/27/2022 11:06AM LastUpdateBy: Will Linville LastUpdatedDate: 11/27/2022 11:06AM |
Type: condition Title: Petition Number Description: Petition 2022-110 Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 11:24AM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |
Type: condition Title: Connection to South Parcel Description: Please include internal connection to south parcel. Discipline: Entitlement Services Status: Open Target: RZ-1 CreatedByName: Maxx Oliver CreatedDate: 11/28/2022 11:26AM LastUpdateBy: Maxx Oliver LastUpdatedDate: 11/30/2022 11:59AM |