Permits you can apply with Full Registration:

Building Permits
Building Permits can directly apply Building Expected time line to get permit 1st reviewed/issued
ALL available Building Permits on ACA up to 15 days
Solar Photovoltaic System up to 5-15 days *
Window replacement in existing openings If correctly submitted, up to 1-5 days *; zoning included in time
Kitchen remodel with no change to wall layout If correctly submitted, up to 1-7 days * ; zoning included in time
Bathroom remodel with no change to wall layout If correctly submitted, up to 1-7 days * ; zoning included in time
Mechanical, Electrical, and Plumbing permits If correctly submitted, up to 1-5 days *; zoning included in time
Reroofing certificate If correctly submitted, 1-3 Business Days
Insulation certificate If correctly submitted, 1-3 Business Days

You will be able to apply for building permits for the following projects by filling out a building worksheet (BW):

Building Permits can apply Indirectly by using  BW.
Expected time line to get permit issued
Limited Building Permits such as the following
1-2 weeks Plus 1-7 Business Days or longer
ADU
up to 10 days 1st review; 4 weeks plan check;  10 days final/ issuance
ADU Pre-Approved Plans
up to 10 days 1st review;3 weeks plan check;  10 days final/ issuance
Additions less than 1000 sq ft
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Additions more than 1000 sq ft
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
New Building
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Cannabis - Other
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Cannabis Certificate of Occupancy
up to 3 weeks review/issued
Commerical Tenant Improvements
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Decks
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Detached Garages and Carports
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Electronic Vehicle Charging
10 days 1st review/issuance
Fences
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Signs - New
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Signs - Change Face
1-5 days
Foundation Repair & Replacement
10 days 1st review/issuance
Termite Repair
10 days 1st review/issuance
Kitchen or Bath Remodel - Wall Changes
up to 6 weeks
Siding & Stucco Replacement
10 days 1st review/issuance
Seismic Retrofit
10 days 1st review
Telecommunications
up to 10 days 1st review; 4 weeks plan check;  10 days final/ issuance
Mandatory Soft Story Program
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Multiple Items for same parcel
10 days 1st review
Revisions to Approved Plans
10 days 1st review



You will be able to apply for zoning approval for the following projects by filling out a zoning worksheet (ZW):

Planning  Permits can apply by using ZW
Expected time line to get permit issued
Limited Planning Permits such as
1-2 weeks Plus 1-7 Business Days or longer
ADU
10 days
ADU - Pre-approved plans
10 days
Additions less than 1000 sq ft
10-15  days
Additions more than 1000 sq ft
10-15  days; or Assignment 4-6 weeks, plus min. of 4-6 months for Issuance, depending on complexity
New Construction
Assignment 4-6 weeks, plus min. of 4-6 months for Issuance
Cannabis
10-15  days
Creek Protection
10-15  days CAT I or II; CAT III or IV - Assignment 4-6 weeks, plus min. of 4-6 months for Issuance
Decks
10-15  days
Detached Garages and Carports
10-15  days
Electronic Vehicle Charging
10-15  days
Signs and Fences (New)
1-5 days; or  Assignment 4-6 weeks, plus min. of 4-6 months for Issuance, depending on complexity
Telecommunications
10  days
Outdoor Dining & Retail
1-5 days
New Housing
Assignment 4-6 weeks, plus min. of 4-6 months for Issuance
Tree Removal/Tree Protection
6 weeks 1st review; then assigned to Tree Division for 2nd review up to 12 weeks
All Other Applications
Assignment 4-6 weeks, plus a min. of 6-9 months for Issuance
Revisions to Approved Plans
Min. 3-5 weeks