You will start with Pre-application BW. Once you pass review, you will be able to apply for a real permit for the below projects

Building Permits can apply Indirectly by using  BW.
Expected time line to get permit issued
Limited Building Permits such as the following
1-2 weeks Plus 1-7 Business Days or longer
ADU
up to 10 days 1st review; 4 weeks plan check;  10 days final/ issuance
ADU Pre-Approved Plans
up to 10 days 1st review;3 weeks plan check;  10 days final/ issuance
Additions less than 1000 sq ft
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Additions more than 1000 sq ft
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
New Building
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Cannabis - Other
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Cannabis Certificate of Occupancy
up to 3 weeks review/issued
Commerical Tenant Improvements
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Decks
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Detached Garages and Carports
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Electronic Vehicle Charging
10 days 1st review/issuance
Fences
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Signs - New
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Signs - Change Face
1-5 days
Foundation Repair & Replacement
10 days 1st review/issuance
Termite Repair
10 days 1st review/issuance
Kitchen or Bath Remodel - Wall Changes
up to 6 weeks
Siding & Stucco Replacement
10 days 1st review/issuance
Seismic Retrofit
10 days 1st review
Telecommunications
up to 10 days 1st review; 4 weeks plan check;  10 days final/ issuance
Mandatory Soft Story Program
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance
Multiple Items for same parcel
10 days 1st review
Revisions to Approved Plans
10 days 1st review


You will start with Pre-application ZW. Once you pass review, you will be able to apply for a real permit for the below projects

Planning  Permits can apply by using ZW
Expected time line to get permit issued
Limited Planning Permits such as
1-2 weeks Plus 1-7 Business Days or longer
ADU
10 days
ADU - Pre-approved plans
10 days
Additions less than 1000 sq ft
10-15  days
Additions more than 1000 sq ft
10-15  days; or Assignment 4-6 weeks, plus min. of 4-6 months for Issuance, depending on complexity
New Construction
Assignment 4-6 weeks, plus min. of 4-6 months for Issuance
Cannabis
10-15  days
Creek Protection
10-15  days CAT I or II; CAT III or IV - Assignment 4-6 weeks, plus min. of 4-6 months for Issuance
Decks
10-15  days
Detached Garages and Carports
10-15  days
Electronic Vehicle Charging
10-15  days
Signs and Fences (New)
1-5 days; or  Assignment 4-6 weeks, plus min. of 4-6 months for Issuance, depending on complexity
Telecommunications
10  days
Outdoor Dining & Retail
1-5 days
New Housing
Assignment 4-6 weeks, plus min. of 4-6 months for Issuance
Tree Removal/Tree Protection
6 weeks 1st review; then assigned to Tree Division for 2nd review up to 12 weeks
All Other Applications
Assignment 4-6 weeks, plus a min. of 6-9 months for Issuance
Revisions to Approved Plans
Min. 3-5 weeks