You will start with Pre-application BW. Once you pass review, you will be able to apply for a real permit for the below projects
Building Permits can apply Indirectly by using BW. |
Expected time line to get permit issued |
Limited Building Permits such as the following |
1-2 weeks Plus 1-7 Business Days or longer |
ADU |
up to 10 days 1st review; 4 weeks plan check; 10 days final/ issuance |
ADU Pre-Approved Plans |
up to 10 days 1st review;3 weeks plan check; 10 days final/ issuance |
Additions less than 1000 sq ft |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Additions more than 1000 sq ft |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
New Building |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Cannabis - Other |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Cannabis Certificate of Occupancy |
up to 3 weeks review/issued |
Commerical Tenant Improvements |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Decks |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Detached Garages and Carports |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Electronic Vehicle Charging |
10 days 1st review/issuance |
Fences |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Signs - New |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Signs - Change Face |
1-5 days |
Foundation Repair & Replacement |
10 days 1st review/issuance |
Termite Repair |
10 days 1st review/issuance |
Kitchen or Bath Remodel - Wall Changes |
up to 6 weeks |
Siding & Stucco Replacement |
10 days 1st review/issuance |
Seismic Retrofit |
10 days 1st review |
Telecommunications |
up to 10 days 1st review; 4 weeks plan check; 10 days final/ issuance |
Mandatory Soft Story Program |
Up to 5 weeks review; 5-7 plan check review; 5 weeks issuance |
Multiple Items for same parcel |
10 days 1st review |
Revisions to Approved Plans |
10 days 1st review |
You will start with Pre-application ZW. Once you pass review, you will be able to apply for a real permit for the below projects
Planning Permits can apply by using ZW |
Expected time line to get permit issued |
Limited Planning Permits such as |
1-2 weeks Plus 1-7 Business Days or longer |
ADU |
10 days |
ADU - Pre-approved plans |
10 days |
Additions less than 1000 sq ft |
10-15 days |
Additions more than 1000 sq ft |
10-15 days; or Assignment 4-6 weeks, plus min. of 4-6 months for Issuance, depending on complexity |
New Construction |
Assignment 4-6 weeks, plus min. of 4-6 months for Issuance |
Cannabis |
10-15 days |
Creek Protection |
10-15 days CAT I or II; CAT III or IV - Assignment 4-6 weeks, plus min. of 4-6 months for Issuance |
Decks |
10-15 days |
Detached Garages and Carports |
10-15 days |
Electronic Vehicle Charging |
10-15 days |
Signs and Fences (New) |
1-5 days; or Assignment 4-6 weeks, plus min. of 4-6 months for Issuance, depending on complexity |
Telecommunications |
10 days |
Outdoor Dining & Retail |
1-5 days |
New Housing |
Assignment 4-6 weeks, plus min. of 4-6 months for Issuance |
Tree Removal/Tree Protection |
6 weeks 1st review; then assigned to Tree Division for 2nd review up to 12 weeks |
All Other Applications |
Assignment 4-6 weeks, plus a min. of 6-9 months for Issuance |
Revisions to Approved Plans |
Min. 3-5 weeks |