How to resolve the H795 inspection
Use this link to schedule a construction inspection with the Health District = https://forms.washoecounty.us/f/PermitInspectionRequest -----
Use this email to resolve a construction inspection that is scheduled with the Health District = ehsplanreview@washoecounty.us ------
https://nvbpels.org/pdfs/2020-BLUE-BOOK.pdf
-----------------------------------------------------------
o H795 inspection required = The project proposes to construct new water infrastructure for a proposed 12-story student housing building at 15th Street + North Virginia Street (parcel 017-015-13).
-----------------------------------------------------------
To resolve the H795 inspection, the contact shall email the following information to ehsplanreview@washoecounty.us: -----
>>> Documentation from the water company affirming that construction is complete and complies with code. -----
>>> The passing backflow test report for the single 4-inch domestic RPPA backflow, the two 8-inch fire DCDA backflow and the single 1.5-inch irrigation RPPA backflow assembly โ here is an example of a backflow test report === https://tmwa.com/wp-content/uploads/docs/Customer_Services/Backflow/TEST_FORM_20080421.pdf. -----
>>> Photographs showing that the single 4-inch domestic RPPA backflow, the two 8-inch fire DCDA backflow and the single 1.5-inch irrigation RPPA backflow assembly are installed. -----
>>> The as-built construction documents if the design changes. -----
Include permit number BLD21-04798E and an explanation in the subject line of the email.
-----------------------------------------------------------
* The submittal for permit BLD21-04798E was received: December 4, 2020 and February 26, 2021 (stamped, signed and dated January 17, 2021 and stamped approved by the water company on January 28, 2021). ----------
* The submittal for permit BLD21-04798E was reviewed: December 7, 2020 and March 2, 2021 (approved).
Applied | Notice | 03/02/2021